Toward autonomous design of AI power infrastructure

Dhruv Suri

As AI grows, supplying data centers with enough electricity is only one challenge. A key risk facing AI infrastructure is when thousands of GPUs change their power demand at once. The equipment between the grid and the chips must respond quickly enough to keep computing work running within electrical limits.

Engineers must decide how much power equipment and energy storage to install, and how to control them. These choices affect cost and reliability. We use AI agents, energy-specific foundation models, and simulation harnesses to help engineers compare these choices and identify weak designs before committing to hardware.

In a simulated 96-rack campus, searching equipment and controller settings together found designs that served more demand than tuning them separately. Both approaches received the same budget of 1,536 evaluations. Sequential tuning remained competitive on equipment use and reducing power swings. In a separate power-conversion study, a revised design passed all 9,216 new scenarios, including severe disturbances and aged components.

For data center developers, this approach could help compare equipment and control choices before purchasing hardware, with the aim of serving more computing demand within electrical limits. Operators and equipment suppliers could use it to identify weak designs early and test whether changes to storage or controls would improve performance before making changes on site.

NVIDIANVIDIAVoltage prediction models built with
NVIDIA PhysicsNeMo

AI workloads need steady power as demand changes

Thousands of GPUs can increase their electricity demand at the same time. If the power system cannot respond quickly enough, voltage can fall and computing work can be interrupted. Engineers need to know how much equipment to install and how to control it before a data center is built.

Consider a sudden increase in GPU demand. Capacitors, which store small amounts of energy close to the chips, respond first. Power converters adjust the electricity to the voltage the chips need, while batteries support longer changes in demand. These devices have to work together. A system may keep voltage steady at first but run out of stored energy before demand returns to normal.

NVIDIA’s 800V DC architecture distributes power at a higher voltage, reducing the current needed to deliver the same power. It also simplifies power delivery to dense GPU racks. Engineers still need to decide how much storage to install, how large the converters should be, and how they should respond when demand changes.

Larger converters and more storage add cost. But equipment size alone does not tell us whether a design will work: the controller, which tells equipment how to respond, matters too. Our work tests these choices together, so engineers can assess a design before committing to hardware.

The importance of designing power delivery from grid to chip

Electricity passes through several stages before it reaches a chip, and decisions at one stage affect the others. For example, storage near the chips can absorb a sudden increase in demand, reducing the immediate power change seen by the campus and grid. But that storage then needs to recharge, creating another demand that the upstream equipment must supply.

Checking each stage separately can miss these interactions. A converter may meet its own specifications while the wider system still runs short of stored energy or exceeds a grid-connection limit. Designing from grid to chip means testing whether the equipment and controls work together across the whole power path. We organize our work around four parts of that system.

  1. Grid–campus network. We model how changes in campus demand affect grid voltage and the loading of lines and equipment.
  2. Campus power and control. We study how batteries, fast storage, and decisions about how much workload to serve can manage changes in demand.
  3. 800V DC power conversion. We test the equipment and controls that deliver power from the DC supply to lower-voltage circuits.
  4. Chip-level power delivery. We check whether local circuits can keep voltage steady when a chip’s current demand changes quickly.
The electrical hierarchy from the grid connection to the chip. The 0.8V core rail is a synthetic study assumption.The electrical hierarchy from the grid connection to the chip. The 0.8V core rail is a synthetic study assumption.
Figure 1. Animation illustrates the direction of power delivery. The electrical hierarchy from the grid connection to the chip. The 0.8V core rail is a synthetic study assumption.

Our goal was to build an AI agent to coordinate these studies. For example, if a design runs out of stored energy, the agent could increase the reserve, change the controller settings, and run the test again. Learned models would help it choose promising candidates; electrical simulators would check them. The experiments below test the parts needed for this workflow. As a next step, we are connecting them into an autonomous loop.

The diagram shows how an agent could use electrical simulations to choose control actions and improve its prediction models. Equipment stays fixed during each test, while results from new and earlier tests train the models. The planning and learning loop shown here is the proposed next integration stage.The diagram shows how an agent could use electrical simulations to choose control actions and improve its prediction models. Equipment stays fixed during each test, while results from new and earlier tests train the models. The planning and learning loop shown here is the proposed next integration stage.
Figure 2. The diagram shows how an agent could use electrical simulations to choose control actions and improve its prediction models. Equipment stays fixed during each test, while results from new and earlier tests train the models. The planning and learning loop shown here is the proposed next integration stage.

We ran the experiments below with ANDES, OpenDSS, PYPOWER, Xyce, ngspice, and NVIDIA PhysicsNeMo. Connecting the workflow to PSS/E, PSCAD, ETAP, and LTspice is currently ongoing.

The diagram shows how candidate equipment and controller settings move from model predictions to detailed electrical checks. The completed studies use open simulation tools; connections to PSS/E, PSCAD, ETAP, and LTspice are being developed.The diagram shows how candidate equipment and controller settings move from model predictions to detailed electrical checks. The completed studies use open simulation tools; connections to PSS/E, PSCAD, ETAP, and LTspice are being developed.
Figure 3. The diagram shows how candidate equipment and controller settings move from model predictions to detailed electrical checks. The completed studies use open simulation tools; connections to PSS/E, PSCAD, ETAP, and LTspice are being developed.

Joint optimization of equipment and controller settings

We compared two ways to design a 96-rack campus power system: sequential tuning and joint search. Sequential tuning first chose controller settings on conservatively sized equipment, then kept those settings fixed while choosing equipment sizes. Joint search varied both together. Each approach received 1,536 evaluations and used the same controller structure, disturbances, and operating limits.

Joint search found designs that supplied a larger share of the requested demand while meeting the study’s electrical requirements. It did so by adjusting how much demand to admit alongside the equipment and other controller settings. For a developer, this points to an important design opportunity: evaluate the hardware and its operating strategy together when deciding how much demand the campus can serve.

The comparison also shows tradeoffs. Sequential tuning remained competitive on equipment use and reducing power swings.

The charts compare joint search with sequential tuning, each given 1,536 evaluations. The left panel shows designs that passed the development tests; the right shows selected designs that also passed new tests. Lower unserved energy means more demand was supplied. The equipment score measures component requirements, not dollar cost.The charts compare joint search with sequential tuning, each given 1,536 evaluations. The left panel shows designs that passed the development tests; the right shows selected designs that also passed new tests. Lower unserved energy means more demand was supplied. The equipment score measures component requirements, not dollar cost.
Figure 4. The charts compare joint search with sequential tuning, each given 1,536 evaluations. The left panel shows designs that passed the development tests; the right shows selected designs that also passed new tests. Lower unserved energy means more demand was supplied. The equipment score measures component requirements, not dollar cost.

We also tested how equipment and control choices affect voltage and stored energy in a separate power-conversion model.

We simulated a power system that steps an 800V DC supply down to 12V and then to a 0.8V chip supply. We tested 6,144 combinations of equipment and controller settings, varying nine choices such as converter size, stored energy, and response speed. Each design faced the same 24 disturbances, for a total of 147,456 simulations.

A design had to keep all three voltage levels between 90% and 110% of their target values and retain at least 10% of its usable stored energy. Of the designs tested, 1,879 met both requirements. Some kept voltage within range but depleted their energy reserve. A voltage check alone would have missed those failures.

The charts show which of the 6,144 designs met both voltage and stored-energy requirements. The left panel shows how designs are distributed across equipment requirements and voltage margin. The right separates passing designs from voltage failures, energy failures, and numerical failures. The equipment score is not a dollar cost.The charts show which of the 6,144 designs met both voltage and stored-energy requirements. The left panel shows how designs are distributed across equipment requirements and voltage margin. The right separates passing designs from voltage failures, energy failures, and numerical failures. The equipment score is not a dollar cost.
Figure 5. The charts show which of the 6,144 designs met both voltage and stored-energy requirements. The left panel shows how designs are distributed across equipment requirements and voltage margin. The right separates passing designs from voltage failures, energy failures, and numerical failures. The equipment score is not a dollar cost.

We tested 12 promising designs on more scenarios, then increased one design’s energy reserve to 24 kJ. We kept its equipment and controller settings fixed for the final test. It passed 48 extreme test cases and 9,216 new scenarios covering mild disturbances, severe disturbances, and aged components. Even in the aged-component tests, its remaining energy reserve never fell below 30.1%.

The chart shows the voltage and stored-energy margins of the fixed 24 kJ design across 3,072 new scenarios in each of three groups. Every scenario met both requirements. Colored contours show where results cluster; the lowest voltage margin and lowest energy reserve can occur at different times.The chart shows the voltage and stored-energy margins of the fixed 24 kJ design across 3,072 new scenarios in each of three groups. Every scenario met both requirements. Colored contours show where results cluster; the lowest voltage margin and lowest energy reserve can occur at different times.
Figure 6. The chart shows the voltage and stored-energy margins of the fixed 24 kJ design across 3,072 new scenarios in each of three groups. Every scenario met both requirements. Colored contours show where results cluster; the lowest voltage margin and lowest energy reserve can occur at different times.

Learning new operating conditions with NVIDIA PhysicsNeMo

A model trained on today’s conditions must stay useful as workloads change and equipment ages. Using NVIDIA PhysicsNeMo, we trained a model to predict how voltage changes during a disturbance. Each update used both new experiments and earlier examples. We accepted it only if it improved on the new conditions and remained accurate enough on all the earlier ones.

The chart shows how voltage-prediction error changes as the model learns new operating conditions. Teal markers show updates that reuse earlier experiments, and orange markers show updates trained only on new conditions, with equal training budgets. Markers show averages across three training runs, and shading and bars show their range. All predictions are evaluated on tests excluded from training.The chart shows how voltage-prediction error changes as the model learns new operating conditions. Teal markers show updates that reuse earlier experiments, and orange markers show updates trained only on new conditions, with equal training budgets. Markers show averages across three training runs, and shading and bars show their range. All predictions are evaluated on tests excluded from training.
Figure 7. The chart shows how voltage-prediction error changes as the model learns new operating conditions. Teal markers show updates that reuse earlier experiments, and orange markers show updates trained only on new conditions, with equal training budgets. Markers show averages across three training runs, and shading and bars show their range. All predictions are evaluated on tests excluded from training.

A brief voltage dip can make a design fail even when voltage looks acceptable for the rest of the test. We trained a separate model on 12,288 experiments to predict whether voltage would stay within the required limits. We calibrated its estimates on separate cases before evaluating it on new tests.

Across 3,072 new tests, the model selected 2,057 cases as meeting the voltage requirement. Detailed simulations confirmed 2,056 of them. One failed. This makes the model useful for selecting candidates to test, while the final decision still requires electrical simulation and a check of the remaining energy reserve.

The chart shows how often the learned voltage model selected a case that passed detailed simulation. It accepted 831 mild, 669 severe, and 557 aged cases from 1,024 tests in each group. One accepted severe case failed the voltage check. Final design approval also requires checking stored energy.The chart shows how often the learned voltage model selected a case that passed detailed simulation. It accepted 831 mild, 669 severe, and 557 aged cases from 1,024 tests in each group. One accepted severe case failed the voltage check. Final design approval also requires checking stored energy.
Figure 8. The chart shows how often the learned voltage model selected a case that passed detailed simulation. It accepted 831 mild, 669 severe, and 557 aged cases from 1,024 tests in each group. One accepted severe case failed the voltage check. Final design approval also requires checking stored energy.

Verifying electrical performance from chip to grid

We also tested a detailed circuit model close to the chip. It includes the switches that convert power and the controllers that regulate voltage. After startup, we increased the chip’s current demand from 400 A to 1,000 A while also changing the input voltage.

All three voltage levels stayed within the study limits. We checked the circuit in two simulators, Xyce and ngspice, and repeated the calculation with smaller time steps. We also checked that the simulated energy flows balanced. The remaining discrepancy was approximately 0.003% of input energy.

The plots show how the circuit responds when chip demand rises and the input voltage changes. The upper panels show the overall response, with shaded bands retaining rapid voltage fluctuations. The lower panels zoom in on the first 60 microseconds after the demand increase. These results come from a synthetic circuit model.The plots show how the circuit responds when chip demand rises and the input voltage changes. The upper panels show the overall response, with shaded bands retaining rapid voltage fluctuations. The lower panels zoom in on the first 60 microseconds after the demand increase. These results come from a synthetic circuit model.
Figure 9. The plots show how the circuit responds when chip demand rises and the input voltage changes. The upper panels show the overall response, with shaded bands retaining rapid voltage fluctuations. The lower panels zoom in on the first 60 microseconds after the demand increase. These results come from a synthetic circuit model.

At the other end of the system, we checked whether the campus could operate within the grid’s voltage and equipment limits. All 576 operating points, drawn from 288 new scenarios, passed. The lowest voltage was 96.09% of its target, and the most heavily loaded transmission line reached 72.9% of its rating. These tests assumed a fixed amount of voltage support at the grid connection, modeled as an ideal 50 Mvar reactive-power source.

Important research contributions

  1. Equipment and control affect performance together: We tested combinations of component sizes and controller settings, then compared joint and sequential search under the same evaluation budget. Under the same search budget, joint search found designs that served more demand, while sequential tuning remained competitive on equipment use and power smoothing.
  2. Models must retain what they have learned: We updated voltage-prediction models using both new and earlier experiments. Each update had to improve on the new conditions while meeting accuracy requirements on the earlier ones. We repeated training three times with different random starting values.
  3. Electrical simulations must check model predictions: Our voltage-screening model selected 2,057 test cases, of which 2,056 passed detailed verification. Separate circuit tests used two simulators, smaller time steps, and energy-balance checks to examine the numerical results.

Toward an AI engineer for power infrastructure

We tested these methods in simulation using public grid models and synthetic equipment. The results show how particular designs respond under the conditions we tested.

For data center developers, operators, and equipment designers, connecting these models would make it possible to test how a change affects the wider system. An engineer could compare storage sizes or controller settings and check whether they keep chips supplied while reducing power swings at the grid connection.

Today, these questions span tools that model different parts of the electrical system. Our proposed agent would coordinate those studies and use the results to choose the next design to test. The aim is to catch failures earlier and explore more equipment-and-control combinations. The individual capabilities are tested; integrated operation and validation with real equipment remain the next steps.

Extended results: Design limits and margins

The figures below show the supporting tests, including how the grid and campus models exchange information, how designs differ, and how much margin remains before a limit is reached.

The plots show how campus demand affects grid and rack voltages and generator speeds during a 0.3-second test. The grid and campus models exchange results until their answers agree, which took nine rounds. The voltage band spans the 12 modeled rack loads.The plots show how campus demand affects grid and rack voltages and generator speeds during a 0.3-second test. The grid and campus models exchange results until their answers agree, which took nine rounds. The voltage band spans the 12 modeled rack loads.
Extended data 1. The plots show how campus demand affects grid and rack voltages and generator speeds during a 0.3-second test. The grid and campus models exchange results until their answers agree, which took nine rounds. The voltage band spans the 12 modeled rack loads.
The chart compares equipment sizes and controller settings across 12 designs that balance equipment requirements against voltage margin. Each column represents one design choice, making different combinations visible. The two controller-gain axes use logarithmic scales.The chart compares equipment sizes and controller settings across 12 designs that balance equipment requirements against voltage margin. Each column represents one design choice, making different combinations visible. The two controller-gain axes use logarithmic scales.
Extended data 2. The chart compares equipment sizes and controller settings across 12 designs that balance equipment requirements against voltage margin. Each column represents one design choice, making different combinations visible. The two controller-gain axes use logarithmic scales.
The plots show how close the fixed 24 kJ design came to its voltage and stored-energy limits across 3,072 scenarios in each group. The curves reveal the least favorable results, while intervals show the spread across scenarios. Circles mark medians, and ticks mark the lowest observed margins.The plots show how close the fixed 24 kJ design came to its voltage and stored-energy limits across 3,072 scenarios in each group. The curves reveal the least favorable results, while intervals show the spread across scenarios. Circles mark medians, and ticks mark the lowest observed margins.
Extended data 3. The plots show how close the fixed 24 kJ design came to its voltage and stored-energy limits across 3,072 scenarios in each group. The curves reveal the least favorable results, while intervals show the spread across scenarios. Circles mark medians, and ticks mark the lowest observed margins.
The charts show how selected campus designs performed on 96 new scenarios in each of three groups. They compare demand left unserved, frequency changes, and storage levels at the end of each test. Points show individual scenarios, diamonds mark the worst result, and colored lines mark the operating limits.The charts show how selected campus designs performed on 96 new scenarios in each of three groups. They compare demand left unserved, frequency changes, and storage levels at the end of each test. Points show individual scenarios, diamonds mark the worst result, and colored lines mark the operating limits.
Extended data 4. The charts show how selected campus designs performed on 96 new scenarios in each of three groups. They compare demand left unserved, frequency changes, and storage levels at the end of each test. Points show individual scenarios, diamonds mark the worst result, and colored lines mark the operating limits.
The plots show grid voltage and line loading across 192 operating points in each of three groups. These checks test whether campus demand stays within grid operating limits, assuming a fixed source of voltage support. They are separate from the simulations of how the campus responds over time.The plots show grid voltage and line loading across 192 operating points in each of three groups. These checks test whether campus demand stays within grid operating limits, assuming a fixed source of voltage support. They are separate from the simulations of how the campus responds over time.
Extended data 5. The plots show grid voltage and line loading across 192 operating points in each of three groups. These checks test whether campus demand stays within grid operating limits, assuming a fixed source of voltage support. They are separate from the simulations of how the campus responds over time.

References

Selected architecture papers, learning methods, and simulation tools cited in the technical article.

  • - NVIDIA’s 800V DC architecture: An introduction to higher-voltage power delivery and energy storage for AI data centers.
  • - 800V DC Architecture for Next-Generation AI Infrastructure: NVIDIA’s technical white paper on the power architecture.
  • - Power Stabilization for AI Training Datacenters: Research on the power swings caused by AI training workloads and ways to manage them.
  • - NVIDIA PhysicsNeMo: The physics-based machine-learning framework used to train our electrical response models. The reported experiments used version 1.3.0.
  • - Fourier Neural Operator: The learning method used to predict how voltage changes over time.
  • - ANDES: The power-system modeling framework used in our dynamic grid–campus study.
  • - OpenDSSDirect.py: The Python interface to OpenDSS used for distribution-network calculations.
  • - IEEE 13-node test feeder: A public distribution-network example referenced in the technical article.
  • - Xyce: Sandia National Laboratories’ circuit simulator. The reported circuit experiments used version 7.10.
  • - ngspice: The circuit simulator used for independent verification, with its user documentation. The technical article references manual version 47.